A beam and block floor in a new house or an extension is building work, so it has to meet the Building Regulations. The rules themselves are short. The detail sits in the Approved Documents, the government’s guidance on how to meet them. This guide goes through the parts that touch a beam and block floor, in plain words, and says what each one means for your job.
It covers England. Wales, Scotland and Northern Ireland have their own versions, which differ in places.
The rules at a glance
| Part | Covers | For your floor |
|---|---|---|
| A | Structure | Beams sized by calculation for the span and load |
| C | Damp and ground gas | A ventilated void, vents, and a membrane where needed |
| L | Energy | Insulation to reach the floor U-value |
| E | Sound | Weight, screed and ceiling for upper floors |
| B | Fire | Garages and upper floors |
| H | Drainage | Drains under the floor and through walls |
Part A: structure
The floor has to carry its own weight and everything on it, and pass that load safely to the walls and foundations. For beam and block, that is shown by structural calculations done for your floor. They set the beam depth, the spacing and where beams are doubled up, for example under a block partition.
- Standards: British Precast, the trade body for precast concrete, says floor beams are designed to BS EN 15037-1 and BS EN 1992-1-1, and should carry the CE mark or have it on the delivery paperwork.
- Bearing: British Precast gives a nominal 100mm end bearing on masonry and 75mm on steel. Your layout drawing shows the bearing for each wall.
- No cutting: beams are made to length for the job. They must never be cut, notched or drilled on site.
Our guides to layouts and calculations and spans go into more detail.
Part C: damp, ventilation and ground gas
This is the part with the most to say about a suspended ground floor. Approved Document C (paragraph 4.19) says a suspended concrete floor will meet the requirement if it has:
- A ventilated air space: at least 150mm clear from the ground to the underside of the floor, or to the insulation if there is any under it.
- Vents on opposite sides: openings in two opposing outside walls, placed so air has a free path to all parts of the void.
- Enough vent area: not less than 1,500mm² for each metre run of outside wall, or 500mm² for each square metre of floor, whichever is greater.
- Pipes and grilles: any pipe carrying the air should be at least 100mm across, and the vents need grilles that keep vermin out without choking the air flow.
- A damp-proof membrane: where the ground under the floor has been dug below the lowest level of the ground around it and will not be drained effectively.
Where the floor has to sit close to the ground to give level access at the door, Approved Document C notes that the void can be vented through offset (periscope) ventilators.
The same document explains why suspended floors are so common on made-up ground. It warns that a slab on more than 600mm of hardcore risks settlement and cracking, and advises a suspended floor instead.
Radon: in parts of the country, new homes and extensions need radon protection. Approved Document C points to BRE report BR 211, which sets out basic protection where 3% to 10% of homes are predicted to be at or above the radon Action Level, and full protection where it is more than 10%. On a beam and block floor that usually means a radon membrane across the floor, with the ventilated void helping too. Check this early, because the membrane has to be detailed at the walls.
See suspended ground floors and floor details for sections and air brick numbers.
Part L: insulation and energy
Approved Document L (volume 1, 2021 edition) gives a limiting U-value of 0.18 W/m²K for the floor of a new home, and the same figure for a new floor in an extension. The 2026 edition, which takes effect on 24 March 2027, keeps the floor limit at 0.18.
Treat that figure as the worst you may build, not the target. A new home also has to pass an energy calculation for the whole house, and that often needs the floor to do better.
The beams and blocks give very little insulation themselves. The U-value comes from the insulation laid over the deck, or from insulated infill panels used in place of the blocks. The thickness you need depends on the product and on the size and shape of the floor, so it is worked out for each job. See our insulation guide, and the underfloor heating guide if you are heating through the floor.
Part E: sound, for upper floors
Sound rules apply to floors inside a home that sit between rooms, such as a first floor over a living room. Approved Document E lists beam and block as one of its standard answers, internal floor type B (paragraph 5.22):
- Weight: beams and blocks with a mass of at least 220kg per square metre.
- Screed: a bonded screed. A sand and cement screed should be at least 40mm thick.
- Ceiling: a ceiling finish underneath, to the treatment the document sets out.
Floors between separate flats have to meet tougher rules and are normally tested. Our upper floors guide explains more.
Part B: fire, for garages and upper floors
Approved Document B (volume 1) says a garage that is attached to a house, or part of it, should be separated from the rest of the house by construction with at least 30 minutes of fire resistance (REI 30). That includes the floor of a room over the garage.
Where there is a door from the house into the garage, the garage floor should either fall away from the door towards the outside, so spilt fuel runs away, or the door opening should be at least 100mm above the garage floor.
The fire resistance of a floor is shown for the whole build-up, including the ceiling under it. Tell us if the floor sits over a garage and it goes into the design. See garage floors.
Part H: drains under the floor
Drains often run under a suspended floor on their way out of the building. Approved Document H says a drain may run under a building if it has at least 100mm of granular or other flexible fill around the pipe. Where a pipe passes through a wall or footing, it has to be protected from damage if the building settles, for example with a short length of pipe built in with flexible joints close to each face.
Plan pipe and duct positions before the floor is designed. Services pass through the infill blocks, never through a beam.
What Building Control will want to see
For the floor itself, expect to be asked for:
- A beam layout drawing: where each beam goes, its size and spacing, and the bearings.
- Structural calculations: showing the beams are right for the spans and loads on your job.
- The floor build-up: insulation, membrane and screed, with the U-value calculation from whoever is doing your energy assessment.
- Vent positions: air bricks or periscope vents shown on the plans.
The first two come from us with every floor. On site, the inspector will usually want to see the floor before it is covered, so tell them when the beams and blocks are down.
If the home will have a structural warranty, the warranty provider has its own technical standards on top of the Building Regulations. Check those as well, as they can ask for more than the Approved Documents do.
Your Building Control officer has the final say on your job. This guide is a summary to help you plan, not a substitute for their advice or for a design done for your floor.
What happens after you send your plans
- You send your plans. Architect’s drawings are ideal, but we can work from a dimensioned sketch with the inside sizes of each room. Tell us if it is a ground floor, an upper floor or a garage.
- We set out the floor. Our engineers work out the beam depth, the spacing and any doubled beams, and produce the layout drawing and the structural calculations your Building Control officer will ask for. Every floor is designed for the job it goes into.
- You get a fixed price. A clear quote for the design, beams, blocks and delivery.
- Delivered to site. Beams are made to length and delivered with the blocks, with crane offload where needed, ready for your builder to lay.
Send us your plans for a free quote or call 02475 095700.
Frequently asked questions
Does a beam and block floor need Building Regulations approval?
Yes. The floor of a new house or an extension is building work, so it is checked as part of your Building Regulations application. Building Control will normally ask for a beam layout drawing and structural calculations, which we include with every floor.
How much ventilation does a beam and block floor need?
Approved Document C asks for vent openings in two opposing outside walls of not less than 1,500mm² for each metre run of outside wall, or 500mm² for each square metre of floor, whichever is greater. Air must have a free path to all parts of the void.
How deep must the void under a beam and block floor be?
Approved Document C asks for a ventilated air space of at least 150mm clear from the ground to the underside of the floor, or to the insulation if there is any under it. The designer may ask for more on some sites.
What U-value does a beam and block ground floor need?
In England, Approved Document L gives a limiting U-value of 0.18 W/m²K for the floor of a new home or an extension. That is the worst allowed. The energy calculation for a new home often needs the floor to do better.
Does a beam and block floor need a damp-proof membrane?
Approved Document C asks for one where the ground under the floor has been dug below the lowest level of the ground around it and will not be drained effectively. A gas membrane may also be needed in a radon area. Your designer and Building Control will confirm what your site needs.
Do I need structural calculations for a beam and block floor?
Building Control will normally ask for them, along with the layout drawing. They show the beams are the right size and spacing for the spans and loads on your job. We produce both for every floor we supply.