Underfloor heating and beam and block go well together. British Precast, the trade body for precast concrete, describes beam and block floors as ideal bases for underfloor heating. The heating itself does not sit in the beams or the blocks. It sits on top, in the layers your builder adds after the floor is laid. This guide explains the build-up, what the Building Regulations ask for, and what to tell us so the floor is designed for the weight.
How the floor is built up
With a wet system, which is warm water in pipes, the usual order from the bottom up is:
- The ventilated void: the space under a suspended ground floor stays vented, heated floor or not. See our suspended ground floors guide.
- Beams and blocks: laid to the layout drawing and grouted, which gives a solid, level deck.
- Membrane: a damp proof or gas membrane where your designer has called for one.
- Insulation: rigid boards laid on top of the deck. This is what stops the heat going down into the void.
- Heating pipes: fixed on top of the insulation to the heating designer’s layout.
- Screed: laid over the pipes. It holds them in place, spreads the heat and gives the surface for your floor finish.
So the insulation goes above the beams and blocks, not under them. Our floor insulation guide covers the insulation options and the U-value the floor has to reach.
Does underfloor heating change the beam design?
The pipes weigh very little. The screed does not. A screed is a layer of wet-laid material across the whole floor, and its weight sits on the beams for the life of the building. Tiles or stone on top add more.
That is why we ask about the floor finish before we design the floor. A thicker screed or a heavy finish can mean a deeper beam, closer spacing or doubled beams, and it is far easier to allow for it on the drawing than to find out after the beams are made. The figures in our span guide are a first guide only. The layout and calculations for your floor are worked out for your job, using the build-up you tell us about.
What the Building Regulations ask for
Approved Document L (Volume 1, 2021 edition) has a section on underfloor heating in homes. The main points for the floor are:
- Heat loss downwards: ground floors should be insulated to limit heat loss to no more than 10 W/m² (paragraph 6.29).
- Insulation under the heating: where the system runs on and off, or sits over an unheated room, it should be separated from the structural floor by insulation with a thermal resistance of at least 1.25 m²K/W (paragraph 6.30).
- Floors between storeys: an upper floor with underfloor heating should have insulation below the heating of at least 0.75 m²K/W for a wet system, or 0.5 m²K/W for an electric one (paragraph 6.31).
- Controls: every system needs controls to adjust its working temperature, and where the screed is more than 65mm thick the system should turn the room temperature down by itself at night or when the room is empty (paragraph 6.28).
- Electric systems: heating cables go in a screed no more than 60mm thick for direct electric systems, and at least 65mm thick for night storage systems (paragraph 6.33).
- Commissioning: the installed equipment should be commissioned to BS EN 1264-4 (paragraph 8.13).
These sit on top of the normal U-value for the floor, which our insulation guide explains. On most new floors the insulation needed for the U-value is the thicker of the two, but your heating designer and energy assessor will confirm that for your house.
The 2026 edition of Approved Document L takes effect on 24 March 2027. It keeps these rules in much the same form. It asks for the 1.25 m²K/W wherever underfloor heating sits directly above the ground, an unheated space or a space that is only heated some of the time, and it adds that the system should be designed to allow for the floor covering.
Approved Document L also asks for new wet heating systems to be sized to work at a flow temperature of 55°C or lower. Underfloor heating is designed to run with cooler water than radiators, so it fits that rule well.
Choosing the screed
The screed is chosen by you, your heating designer and your screeder, not by us, but we need to know the choice because of its weight.
| Choice | What to know |
|---|---|
| Sand and cement screed | Laid by hand over the pipes. Tell us the thickness so the weight is in the calculations. |
| Liquid screed | Poured and flows around the pipes. The layer below has to be sealed so the screed can’t run through the joints. Follow the screed maker’s instructions. |
| Heavy floor finishes | Stone, thick tiles and their beds add weight on top of the screed. Tell us about them too. |
Whichever you choose, let the screed dry and bring the heating up slowly the first time, as the screed maker and heating installer advise. Rushing it is a common cause of cracked screeds and lifted floor finishes.
Floor depth and levels
Underfloor heating does not need much extra depth by itself, because the pipes sit inside the screed. What sets the depth is the insulation and the screed together. Decide both before the walls are built to level, so the finished floor lines up with your door thresholds and, on an extension, with the floor in the existing house. Our insulation guide shows how to add the build-up together.
Pipes, manifolds and the beams
- Nothing is fixed into the beams: the heating pipes are fixed to the insulation above the deck. Beams are never cut, drilled or notched on site.
- Pipes through the floor: where a supply pipe has to pass through the deck, it goes through the blocks between the beams. Our floor details guide shows how service entries are handled.
- Mark the manifold on your plans: if we know where the manifold and any risers are, the beam positions can be checked against them.
Underfloor heating on an upper floor
Beam and block is used upstairs as well, and underfloor heating works there in the same way: insulation on the deck, pipes on the insulation, screed over the top. The insulation below the heating stops the heat going into the ceiling of the room underneath. An upper floor in concrete also has to be designed into the walls and foundations from the start. Our upper floors guide explains what to plan.
Who does what
| Who | What they look after |
|---|---|
| Us | The beam layout drawing and structural calculations, the beams and blocks, and delivery to site. The design allows for the screed and finishes you tell us about. |
| Your heating designer or installer | The pipe layout, heat output, controls and commissioning. |
| Your energy assessor | The U-value of the floor and the energy calculation for the house. |
| Your builder or screeder | Laying the floor, the insulation and the screed. |
| Building Control | Checking the work. We can’t promise what they will decide, but you will have the floor paperwork they normally ask for. |
What to tell us for a quote
Your plans, or a sketch with the inside sizes of each room, and the site postcode are enough to start. For a heated floor it also helps to know:
- that the floor will have underfloor heating, and in which rooms
- the type and thickness of screed, if you know it yet
- the floor finish, especially stone or large tiles
- where the manifold and any pipes through the floor will be
- any heavy items, such as a bath, a kitchen island or partition walls built off the floor
If you don’t know the screed yet, say so. We’ll tell you what we have allowed for, so your heating designer can work to it.
What happens after you send your plans
A heated floor is priced the same way as any other floor we supply. The quote form asks for your name, phone number, email, and the site address and postcode. Plans help us price the floor accurately, and you can upload them as PDF, image, DWG or ZIP files, but they are not essential.
- You send your plans. Architect’s drawings or a sketch with the inside sizes of each room. Anything that shows the walls and spans.
- We set out the floor. Our engineers work out the beam depth, the spacing and any doubled beams for the screed and finishes you have told us about, and produce the layout drawing and the structural calculations your Building Control officer will ask for.
- You get a fixed price. A clear quote for the design, beams, blocks and delivery.
- Delivered to site. Beams are made to length and delivered with the blocks, with crane offload where needed, ready for your builder to lay.
Send us your plans for a free quote or call 02475 095700.
Frequently asked questions
Can you have underfloor heating on a beam and block floor?
Yes. British Precast describes beam and block floors as ideal bases for underfloor heating. The pipes are laid on insulation on top of the deck and covered with a screed. Tell us about the screed so its weight is allowed for in the design.
Does the insulation go above or below a beam and block floor?
Above. Rigid insulation boards are laid on top of the beams and blocks, the heating pipes sit on the insulation and the screed goes over them. The void under a suspended ground floor is left ventilated.
Does underfloor heating change the beams I need?
It can. The pipes are light, but the screed and any stone or tile finish add weight that the beams carry. A thick screed can mean deeper beams, closer spacing or doubled beams, which is why the floor is designed for your job.
How much insulation is needed under underfloor heating?
Approved Document L (2021 edition) asks for ground floors to lose no more than 10 W/m² downwards, and for at least 1.25 m²K/W of insulation between the heating and the structural floor where the system runs on and off or sits over an unheated room. The floor also has to meet its U-value. Your heating designer and energy assessor work out the thickness.
Can underfloor heating pipes be fixed to the beams?
No. The pipes are fixed to the insulation above the deck. Beams are never cut, drilled or notched on site, and any pipe that has to pass through the floor goes through the blocks between the beams.
Does underfloor heating work on a beam and block upper floor?
Yes. The build-up is the same: insulation on the deck, pipes on the insulation and a screed on top. Approved Document L asks for at least 0.75 m²K/W of insulation below a wet system on a floor between storeys, or 0.5 m²K/W for an electric one.